Are you an electrician working in our service area? Use this section of our site to find resources on our requirements for new services, sub-metered heat, temporary job site power, metering and more. Have more questions? Call us at 800.748.5533.
This section is subject to revision. Roughrider Electric Cooperative is not liable for any faulty wiring done on the secondary side of the electrical service.
Does Roughrider provide the transformer pad?
Yes, but only on units up to 300 KVA. Anything larger will not be provided. Diagrams for concrete pads are available in the Diagrams section below.
Will Roughrider provide the fault current for electricians?
No. We will however provide the impedance so the calculations can be made. Impedance numbers are written on the exterior of the transformers or can be obtained by calling our office.
What is the procedure for having Roughrider make a site visit to open a transformer, de-energize a service or something similar?
Such a visit requires us to schedule a crew to visit the site. Please contact us to schedule a time for us to visit. Scheduling is usually a week out. Plan accordingly.
Transformer Pad Diagrams:
What is necessary to get jobsite temporary power, installation and disconnection?
- Apply for temporary service by specifying it in the request for power form (in addition to the type of main service eventually needed.)
- While we don’t guarantee the availability of temporary service, we provide it as often as possible when the situation dictates. We will disconnect the temporary when we come out to hook up the main meter.
What equipment does an electrician provide for underground jobsite temporary power?
Electricians will install their own pedestal (not one picked up at the cooperative) and run their own wire for the pedestal.
What equipment does an electrician provide for overhead jobsite temporary power?
Roughrider will install all overhead meter loops, risers and temporary meter sockets. Electricians should not attempt to install their own.
For jobsite temporary power, is it ok to use the permanent utility transformer and the primary wire if they have already been set and pulled in? Could an electrician install an additional 2” conduit with the secondary conduit run, then pull wire and set a single phase meter rated for a 200 amps?
Yes, if the transformer is already set this plan works for us.
Overhead Single Phase Service:
We will hang the meter loop during construction. Once the socket is tied in, electricians must provide a wiring certificate and notification that the service is ready to be metered and energized.
Underground Single Phase Service:
- Meter Socket on a building: Electricians provide their own socket, according to our specifications. See our list of part numbers below. Once the socket is tied in, electricians must provide a wiring certificate and notification that the service is ready to be metered and energized.
- Meter Socket on a stub pole: We will install and wire the socket when we build the rest of the service. Electricians must tie in the secondaries, provide a wiring certificate and notify us when it's ready to be metered and energized.
Overhead Three-Phase Service:
We will hang the meter loop during construction. Once the socket is tied in, electricians must provide a wiring certificate and notification that the service is ready to be metered and energized.
Underground Three-Phase Service:
CT Metered: Electricians provide the meter socket, CT enclosure and secondary wiring between the metering and transformer, according to our specifications. See our list of part numbers below. Electricians install a CT enclosure and run the line between the secondary side of the transformer and the CT meter enclosure. CT meters should be placed within 10 feet of the transformer. Roughrider will wire the CT enclosure and place the CT’s in the cabinet. The CT cabinet (CT enclosure) must be a separate unit from the meter socket, which is to be placed next to the CT cabinet. No dual-unit meter and CT enclosure units will be allowed.
All CT Cabinet Wiring:
All single phase and three phase CT cabinets will be wired with line side connections on the top lugs and load side on the bottom lugs. Any service not wired this way will not be energized and the wiring will need to be connected correctly before it will be energized. Roughrider Electric will not be liable for any expense incurred to correct the wiring.
Across the Line Metered:
- Meter Socket on a building: Electricians provide their own socket, according to our specifications. See our list of part numbers below. Once the socket is tied in, electricians must provide a wiring certificate and notification that the service is ready to be metered and energized.
- Meter Socket on a stub pole: We will install and wire the socket when we build the rest of the service. Electricians must tie in the secondaries, provide a wiring certificate and notify us when it's ready to be metered and energized.
What are Roughrider’s regulations on when to use a CT meter versus an across the line meter?
Any service over 200 amps, single or three phase.
Who provides the meter socket?
Electricians.
Who furnishes the CT enclosure/CT meter can?
The electrician.
Who provides the termination points (lugs) in the CT enclosure?
The Electrician.
Does Roughrider have specification on the size or dimensions of the CT enclosure/CT meter can?
No. All we require is that the enclosure be large enough to accommodate the amperage size of your service.
Who provides the conduit wiring?
The electrician.
Who provides and places the CT’s in the CT cabinet?
Roughrider does.
Who will do the wiring in the CT enclosure?
Roughrider will.
Will Roughrider do the wiring for all metering?
Yes.
Who lands the secondary conductors to the transformer?
The electrician installs the secondary wire.
Will the secondary lugs be provided in the transformer?
Yes, Roughrider will give the lugs.
What kind of time frame does it take to get the service hooked up?
As soon as the CT cabinet (if necessary) and meter socket are in place and a wiring certificate is in, Roughrider will get the meter hooked up. We do our best to install a meter within a week of receiving the wiring certificate.
Meter Socket Part Numbers
If you have electric heat as your primary heat source, you are eligible to receive a credit, applied October through April.
To receive credit for your electric heat, you must have a functioning Heat Sub Meter installed.
Please check the breakers on any and all heat or sub meters to ensure the meters are working. The meter’s display should not be blank. If your breakers are on and there is no display on the meter, please contact us at 800-748-5533.
Disclaimer:
It is the responsibility of the member to assure that the Heat Sub Meter is on and functioning properly. Roughrider Electric will not provide heat credits for kWh's not registered on the Heat Sub Meter.
Who provides the socket for the heat meter?
The electrician.
Who wires the heat meter socket?
The electrician.
These are the approved meter sockets for the 3S and 4S heat meters: